What is a reliance letter, and why does a lender ask for one on a site report?

A reliance letter shows up late in a draw package, usually after the site report itself is already done. The borrower's engineer or inspector has walked the asset, written up the findings, and now somebody on the lender side asks: can we rely on this too?
That's the whole function of the letter. It's a short, separate document from the firm that wrote the site report, stating that a named additional party, your fund, your co-investor, the agent bank, can treat that report as if it had been commissioned directly for them. Without it, the report technically only protects whoever paid for it.
Why the report alone isn't enough
A site inspection report is written for its client. If the sponsor hired the engineering firm, the engagement letter, the scope, and the liability all run back to the sponsor. Your fund wasn't a party to that contract, so if the report turns out wrong, your legal standing to go after the firm is thin at best.
Lenders ran into this enough times that it's now standard practice on any deal with outside capital in the stack. The credit committee doesn't want a report they can't stand behind if the asset doesn't match what was represented. A reliance letter extends the firm's professional liability to cover the new party, usually with some conditions: a cutoff date, a cap on damages, maybe a requirement that the relying party had no role in defining the scope of work.
On a project finance deal with a syndicate, you'll sometimes see one report with five or six reliance letters stapled behind it, one for each lender and co-investor in the facility. The underlying report doesn't change. What changes is who can put weight on it.
What this means for your diligence file
Here's the practical catch: a reliance letter extends legal standing, it doesn't improve the underlying work. If the site report says the building is 70% framed and that number came from the sponsor's own progress photos, or from a walkthrough scheduled and escorted by the sponsor's project manager, the reliance letter just means you now have standing to dispute a number you couldn't independently check in the first place.
Associates who've been burned by this tend to ask a second question before the draw goes forward: is there an independent read on the asset that didn't depend on the sponsor scheduling the visit? That's a separate workstream from the reliance letter, and it's the one that actually tells you whether the 70% is real.
Site Verification sits in that gap, alongside the engineer's report and reliance letter rather than replacing them. It's a before/after image pair and progress note pulled from satellite or aerial imagery on your timeline, confirming the footprint matches what's on file and that the claimed progress shows up on the ground, before the wire goes out. No scheduling call to the sponsor, no dependency on whoever walked the site that week.
A few things to check before you sign off
- Who is named on the letter. A reliance letter addressed to "Lender" in a bilateral deal is fine. In a syndicated facility, confirm every participant that needs to rely on the report is named, not just the agent.
- The cutoff date. Reliance letters are dated to the report, not to your draw request. If six months passed between the site visit and this draw, the letter covers conditions as of the old date, not today.
- Caps and carve-outs. Most firms cap their liability under a reliance letter, often at the original fee or some multiple of it. Worth knowing before you count on the letter for more than it's built to deliver.
- Scope language. If the original engagement excluded certain building systems, environmental conditions, or wasn't asked to verify physical progress against a schedule, the reliance letter inherits those same exclusions. It doesn't add scope, it only adds standing.
None of this is a knock on reliance letters. They do exactly what they're designed to do, which is give you legal recourse against the firm that wrote the report. They just don't answer the question of whether the thing being reported on is there. For that, it helps to have a read on the site that didn't run through the sponsor at all.
If the draw date is close and you want a second, independent look at the asset before you sign off, see what Site Verification covers.